SPUSD Elementary Schools | Measure SP Construction Update

South Pasadena Portable to Permanent Classroom Additions - Arroyo Vista, Marengo and Monterey Hills Elementary School

PHOTO: SPUSD | SouthPasadenan.com News | Monterey Hills Elementary

Monterey Hills ES

The construction crew has begun applying exterior stucco and excavating the exterior stairs. The prefabricated elevator is scheduled to be delivered on November 1 and will be placed the same day.

Once the elevator and stairs are set, the retaining wall on the east side can be completed and finish grading will resume. Both the domestic water tie-in and sewer tie-in will be completed soon.

- Advertisement -

Arroyo Vista ES

PHOTO: SPUSD | SouthPasadenan.com News | Arroyo Vista Elementary

The team is preparing concrete walkways and placing flooring inside the building. The new fire lane on the asphalt pavement/playground is scheduled to be installed during the Thanksgiving break to minimize disruption to school activities.

The main electrical switchgear is expected soon and permanent power may be connected prior to the end of the month.

Marengo ES

PHOTO: SPUSD | SouthPasadenan.com News | Marengo Elementary HS

The building’s interior flooring has been completed and requires minimal touch-ups. The perimeter sidewalk is ready for placement and should be completed by the end of the month.

The team will start up the building equipment once the electrical switchgear is fully installed. The new fire lane and playground repairs will be scheduled during Thanksgiving break.