Measure SP Construction Update | May 2018

PHOTO: South Pasadena High School | SouthPasadenan.com

SPHS STEM Building Second-floor framing is underway for the northern section of the new building. Sheathing and roofing for this section is scheduled to begin in June 2018. Workers are preparing the southern portion of the building’s foundation and expect to lay the interior slab in June as well. The project is expected to be complete – on schedule – in December 2018.

SPHS Physical Education and Athletic Facility Planning is on-going for a more fluid transition between the existing gymnasium, athletic field, baseball field, tennis courts and outdoor basketball courts.

SPMS Hard Court & Field Project Recently workers installed the turf and the court equipment. The finishing touches will include new sod and court surfacing prior to the project completion in June 2018. The project will be completed on schedule and on budget.

- Advertisement -

SPMS Old Gymnasium Re-purposing Based on recent testing of the soil and existing interior walls, the team re-evaluated the structural and seismic requirements. The results of the testing will provide a revised structural system and may include cost savings. Final plan submission to the Division of State Architects is expected in June 2018. Construction is expected to begin in Spring 2019.

PHOTO: South Pasadena Middle School | SouthPasadenan.com