SPUSD PRESS RELEASE:
In June the team focused on plastering the exterior of the building and completing the perimeter ‘envelope’. Plaster was applied in three layers; scratch, brown and finish. The finish coat is an integral color plaster that establishes the exterior colors of the building.
With plaster completing on the outside of the building, the project team pushed forward with utility system installations inside. Air duct, fire sprinkler pipe, plumbing lines and electrical conduit are being run throughout the interior. These systems will soon be operational.