SPUSD | SPMS Gym Construction Update

South Pasadena construction update for the South Pasadena Middle School Old Gymnasium Rehabilitation Project

PHOTO: Provided by SPUSD | SouthPasadenan.com News | Construction on the exterior of the old gym at SPMS

SPUSD PRESS RELEASE:

In June the team focused on plastering the exterior of the building and completing the perimeter ‘envelope’. Plaster was applied in three layers; scratch, brown and finish. The finish coat is an integral color plaster that establishes the exterior colors of the building.

With plaster completing on the outside of the building, the project team pushed forward with utility system installations inside. Air duct, fire sprinkler pipe, plumbing lines and electrical conduit are being run throughout the interior. These systems will soon be operational.

PHOTO Provided by SPUSD | SouthPasadenancom News | Bare walls from construction on the interior of the old gym at SPMS

 